Mezzanines for Phoenix and the ValleyLicensed and insured(928) 232-1752

Phoenix Mezzanine Installation (928) 232-1752 Request a quote

Permit guide · 2024 Phoenix code

Mezzanine Permits in Phoenix: The 2024 Code, IBC 505 and ADOSH

A mezzanine in a Phoenix building needs a commercial building permit, filed online through the city's SHAPE PHX portal and drawn to the 2024 Phoenix Building Construction Code. ADOSH, Arizona's own workplace safety program, adds the federal rail, stair and gate rules. This guide walks through each step and number.

Underside of a white mezzanine deck with LED fixtures and red sprinkler pipes

Does a Mezzanine in Phoenix Need a Building Permit?

Yes. Under IBC 105.1 as Phoenix adopted it, an owner or agent who intends to "construct, enlarge, alter, repair, move, demolish or change the occupancy" of a building must apply to the building official and get the permit first. Two of the Phoenix exemptions in 105.2 come close to a mezzanine: platforms not more than 30 inches above the adjacent grade, not over a story below and not part of an accessible route, and racks or fixtures up to 5 feet 9 inches that are not an accessible surface. A mezzanine needs 7 feet of clear height below it (IBC 505.2), so it sits far above that line.

  • Needs a permit: a mezzanine, storage deck or walk-on level with 7 feet of headroom under it.
  • May be exempt: a platform 30 inches or lower, with no story below, that is not on an accessible route (105.2).
  • May be exempt: racks, cases and fixtures up to 5 feet 9 inches tall that are not an accessible surface (105.2).
  • Never a pass to skip the code: an exemption does not allow work that breaks the code or other city laws (105.2).

The two exemptions are explained in our guide to the 30-inch and 5-foot-9 rules. We size and draw each deck for mezzanine installation in Phoenix with the permit in mind from the first visit.

Which Building Code Does Phoenix Use for Mezzanines?

The 2024 Phoenix Building Construction Code (PBCC). The City Council adopted it on June 18, 2025, under Ordinance G-7397, and it took effect on August 1, 2025. It adopts the 2024 International Building Code with city amendments, a document Phoenix calls the International Building Code as Amended by the City of Phoenix. Plans first submitted from August 1, 2025 follow the 2024 code, apart from a few listed exceptions, and every plan submitted after December 31, 2025 must. For mezzanine work, Phoenix left Section 505 as written, and its one Table 1607.1 change touches one- and two-family homes.

What Phoenix Changed in the 2024 IBC for Mezzanine WorkCity of Phoenix 2024 IBC amendment sheets, Ordinance G-7397.
Code sectionPhoenix changeWhat it means for a mezzanine
505 Mezzanines and equipment platformsNoneThe model 2024 text applies as printed
Table 1607.1 Live loadsHome row only (one- and two-family dwellings)Commercial and industrial rows keep the model values
1104.4 Accessible routeTitle changed from multistory to multilevelThe route rule reads across multilevel buildings
105.1 PermitsSeparate permits for fire extinguishing and alarm systemsSprinkler or alarm changes need their own fire permit
105.2 Work exempt from permitPhoenix wordingLow platforms and short racks may need no permit
107.1 Construction documentsRegistered design professional as Arizona requiresDrawings come from an Arizona-registered professional

The package also adopts the 2024 International Fire Code with Phoenix amendments. What changed for mezzanines is covered in Phoenix's 2024 code and your mezzanine.

How Is a Commercial Mezzanine Permit Filed in Phoenix?

Online, through the city's SHAPE PHX portal, which has taken new commercial plan review and inspection permits since April 27, 2026. Phoenix requires a commercial building permit for non-residential work, including remodels, additions and tenant improvements, and its submittal checklist lists project types from new buildings to tenant improvements and miscellaneous work. A tenant improvement may raise no site issues, while an addition can. Licensed professionals prepare the plans, and the structural sheets are sealed by a structural or civil engineer registered in Arizona.

  1. We visit, measure the room and its clear height, and note the aisles, doors and dock traffic.
  2. We set the use of the deck and its live load from IBC Table 1607.1.
  3. An Arizona-registered engineer seals the layout and structural drawings, with calculations for vertical and lateral loads.
  4. If the city's project team asks for one, a pre-submittal meeting comes before filing.
  5. The commercial building permit is filed in SHAPE PHX, and plan review fees are paid at submittal.
  6. Reviewers send any corrections; the plans are revised and resubmitted. A third review costs extra.
  7. Sprinkler or alarm changes get their own fire permit (IBC 105.1 as amended).
  8. The contractor's license number is on file before the permit is issued, and permit fees are paid at issuance.
  9. Steel comes from a city-approved fabricator, or the shop work gets special inspection (IBC 1704.2.5).
  10. Our crew installs the mezzanine, the inspections follow, and the posted load signs are in place before the city issues the certificate of occupancy.

The city decides how your project is classed in SHAPE PHX. To ask before filing, contact Phoenix Planning & Development. The full walk-through is in our SHAPE PHX filing guide, and the budget side is on the mezzanine cost guide.

What Does IBC Section 505 Require in Phoenix?

Section 505 treats a mezzanine as an intermediate level inside a story. When it complies, it belongs to the story beneath it and adds neither building area nor a story, though its area joins the fire area. It needs at least 7 feet of clear height above and below, may take up as much as a third of the room, and stays open to the room, with nothing but columns, posts and walls of 42 inches or less in the way. The 2024 text measures the room without its enclosed part and without the mezzanine itself. Exits follow Chapter 10.

Section 505 Limits Under the 2024 Phoenix CodeIBC 2024 Section 505, not amended by Phoenix. Plan review decides your project.
TopicLimit or ruleSection
Story countPart of the story below; adds no building area or story; area counts in the fire area505.2
Headroom7 ft clear above and below the floor construction505.2
Area, generalUp to one-third of the room505.2.1
Area, sprinklered Type I or II with a voice alarm systemUp to one-half of the room505.2.1 exception
Area, special industrial occupancy in Type I or IIUp to two-thirds of the room505.2.1 exception
Measuring the roomLeave out the enclosed portion and the mezzanine's own area505.2.1
Mezzanine plus an equipment platformTwo-thirds of the room for both together505.2.1.1
OpennessOpen; only columns, posts and walls of 42 in or less; listed exceptions505.2.3
ExitsChapter 10 applies505.2.2

Section 505.2.3 relaxes the openness rule in listed cases, such as enclosed space for ten occupants or fewer, a deck served by two or more exits, and a glass-walled control mezzanine in an industrial plant. Equipment platforms are a separate case under 505.3: unoccupied platforms for mechanical or process equipment that are not part of the floor below, stay out of the fire area and never serve as an exit. All the platforms in a room may cover two-thirds of it, sprinklers go both over and under a platform when the standards cited in Section 903.3 call for them, and guards follow 1015.2. If a raised level falls outside Section 505, the code no longer treats it as a mezzanine, and it can count as another story; plan review makes that call. The second-floor page covers that line.

Does a Mezzanine Need an Accessible Route in Phoenix?

The code starts from yes. Phoenix's 1104.4 reads: "At least one accessible route shall connect each accessible story, mezzanine and occupiable roofs in multilevel buildings and facilities." Phoenix renamed the section from multistory to multilevel buildings because the old title had been read as limiting the rule to multistory buildings. The code then lists exceptions, and plan review decides whether any of them fits your building. We do not assume an exception for you; the drawings show the route or the code section that plan review is asked to apply.

  • 1104.4: no route is required to levels with an aggregate area of not more than 3,000 square feet that sit above and below accessible levels. This does not apply to Group M facilities with five or more tenant spaces, health care provider offices, passenger transportation facilities and airports, government buildings, or buildings with four or more dwelling units.
  • 1104.4: levels that contain no accessible elements or other spaces under Section 1108 or 1109 need no route from an accessible level.
  • 1104.4: in a two-story building, a story or mezzanine with an occupant load of five or fewer and no public use space need not be connected by an accessible route.
  • 1103.2.2: spaces within employee work areas must let people with disabilities approach, enter and exit the work area, and meet Sections 907.5.2.3.1, 1009 and 1104.3.1.
  • 1103.2.9: spaces used only by service personnel for maintenance, repair or occasional monitoring of equipment need not meet Chapter 11.

Read how IBC 1104.4 and its exceptions work in Phoenix, or see how raised offices are planned on our mezzanine office page.

Does Arizona Use the Federal OSHA Rules?

Yes, through its own state plan. ADOSH, part of the Industrial Commission of Arizona with its main office in Phoenix, runs workplace safety for most private employers and for state and local government. Arizona Administrative Code R20-5-602 adopts 29 CFR 1910 Subparts B through Z by reference, with amendments as of July 14, 2020. The federal walking-working surfaces rule took effect on January 17, 2017, before that date, so its guardrail, stair, ladder and gate rules in Subpart D apply to Arizona workplaces. ADOSH enforces with the OSHA Field Operations Manual as its guide.

  • Workers on an open side or edge that sits 4 feet or higher over the floor below need a guardrail, a safety net or personal fall protection (1910.28(b)(1)(i)).
  • Hoist areas, where pallets and materials come up to the deck, need protection from falls of 4 feet or more (1910.28(b)(2)(i)).
  • Chains or gates may stand in for a removable guardrail section at a hoist area when the employer shows they are as safe (1910.29(b)(10)).
  • An access hole is guarded by a gate that closes by itself and moves away from the opening, or by an offset that keeps anyone from stepping straight in (1910.29(b)(13)).
  • Stair rails and handrails go on every flight that has at least three treads and four risers (1910.28(b)(11)(ii)).

Some workplaces stay with federal OSHA, including federal employers, contractors on federal establishments where only the federal government has jurisdiction, and Indian reservations. ADOSH also offers on-site consultation to employers. Our ADOSH fall protection guide has the detail.

Pallet gate bay at the edge of a charcoal mezzanine, a pallet of cartons inside and a stair at the end
A two-gate pallet bay at a deck edge, one way to guard a hoist area where loads come up.

Building Code or ADOSH: Which Numbers Apply?

Both, because they answer to different offices. The building code is what Phoenix reviews and inspects on the way to the certificate of occupancy; ADOSH governs the workplace once your team uses the deck. The two often set different numbers for the same part. Guards start at a drop of more than 30 inches under the building code, for example, while the federal rule starts at 4 feet. When the numbers disagree, we size each part to satisfy both documents, so one deck answers to the city and to the employer's safety rules.

Phoenix Building Code Next to ADOSH, Part by PartIBC 2024 as adopted by Phoenix; 29 CFR 1910 as adopted by ADOSH (A.A.C. R20-5-602).
PartBuilding code (IBC 2024, Phoenix)ADOSH (29 CFR 1910)
Where edge protection startsA drop of more than 30 in (1015.2)A drop of 4 ft or more (1910.28(b)(1))
Guard or top rail height42 in minimum (1015.3)42 in, plus or minus 3 in (1910.29(b)(1))
Openings in the guard4 in sphere; 21 in sphere at equipment access walkways and in F, H, S and I-3 areas closed to the public (1015.4)19 in maximum (1910.29(b)(2))
Guard strength200 lb concentrated and 50 plf (1607.9.1)200 lb top rail; 150 lb midrail (1910.29(b)(3), (b)(5))
Stair riser and tread7 in maximum riser; 11 in minimum tread (1011.5.2)9.5 in maximum riser; 9.5 in minimum tread (1910.25(c))
Stair width44 in, or 36 in below 50 occupants (1011.2)22 in minimum (1910.25(c)(4))
Stair headroom80 in (1011.3)6 ft 8 in (1910.25(b)(2))
Handrail height34 to 38 in (1014.2)30 to 38 in (1910.29(f)(1)(i))

Gates, pallet drops and every rail detail are on our stairs, railings and gates page. Two guides go further: why the guard line sits at 30 inches or 4 feet and building code stairs next to ADOSH stairs. Stairs, gates and deck surfaces are pictured on the mezzanine options page.

Wide charcoal stair with yellow handrails seen head-on from the floor, rising to the deck
Stair width, riser height and handrail height each carry a building code number and an ADOSH number.

What About Projects Outside Phoenix City Limits?

Each city in the Valley runs its own permits, so a deck in Mesa or Tempe is filed with that city, not with Phoenix; city permit records in both list their own mezzanine permits. Unincorporated parts of the county follow Maricopa County. Its Board of Supervisors adopted the 2024 I-Codes and the 2023 NEC on 21 October 2026, effective 20 November 2026. The 2018 I-Codes stay in effect through 20 May 2027 for projects already in review, plans submitted before 20 November 2026 and some case-by-case situations. We confirm the code edition with the building department that holds the permit before anything is drawn.

The cities we cover are listed on our service areas page.

What Must Be Done Before Phoenix Issues the Certificate of Occupancy?

The inspections must close and the floor load signs must be up. Phoenix's adopted IBC 106.1 says that in commercial or industrial buildings, each floor or part of a floor designed for live loads over 50 psf gets durable signs, posted by the owner or the owner's agent where that load applies, and removing or defacing them is unlawful. Under 106.2, Phoenix will not issue the certificate of occupancy before those signs are installed, and 106.3 bars loading any floor beyond what the code permits. Where the steel came from an approved fabricator, its certificate of compliance goes to the building official.

Storage decks, rated 125 or 250 psf in Table 1607.1, sit above the 50 psf line, so they need signs. We post them before the final sign-off on your deck.

Blank aluminium placard on a charcoal mezzanine beam where the load sign goes
A blank plate on the deck fascia, ready for the posted design load.

What Does a Code-Compliant Mezzanine Project Include?

Every Phoenix mezzanine we supply comes with the code checks and the permit steps built into the job. You order it from us, and our own crew puts it up, from the first measurements to the last inspection. We line up the engineer's sealed drawings and the permit filing with the City of Phoenix. A single order and a single crew, with one person to call.

  • Site visit: floor size, clear height, slab and the way stock moves.
  • Layout tested against IBC 505 and the ADOSH rail and stair rules before any steel is bought.
  • Drawings sealed by an Arizona-registered engineer, and the permit filing.
  • Delivery of the columns, beams, deck, stairs, guardrail, gates and any lift.
  • Our crew installs it, then the inspections and the posted load signs.

Sources, read November 2026: City of Phoenix, Building Code (2024 PBCC) · City of Phoenix, 2024 PBCC implementation notice · City of Phoenix, 2024 IBC amendment sheets · City of Phoenix, 2024 IBC Chapter 1 amendments · Phoenix Building Code 2024, Chapter 1, via UpCodes · Phoenix Building Code 2024, Chapter 2 definitions, via UpCodes · Phoenix Building Code 2024, Section 505, via UpCodes · Phoenix Building Code 2024, Chapter 10 means of egress, via UpCodes · Phoenix Building Code 2024, Chapter 11 accessibility, via UpCodes · Phoenix Building Code 2024, Table 1607.1, via UpCodes · Phoenix Building Code 2024, Chapter 17 special inspections, via UpCodes · City of Phoenix, Commercial permits · City of Phoenix, SHAPE PHX · City of Phoenix, Commercial process overview · City of Phoenix, Commercial Building Permit Submittal Checklist (Rev. 06/25) · City of Phoenix, Approved fabricator resources · Maricopa County, 2024 Building Code Implementation · OSHA, Arizona State Plan · Ariz. Admin. Code R20-5-602, via Cornell LII · Federal Register 2016-24557, Walking-Working Surfaces · OSHA 29 CFR 1910.28 · OSHA 29 CFR 1910.29 · A.R.S. 32-1151, contractor license required · OSHA 29 CFR 1910.25

01Code notes

Mezzanine Rules for Phoenix Buildings at a Glance

We test every layout against these points before steel is bought. The city's plan reviewers make the final call for your building.

  1. 01

    Permit first

    Apply and get the permit before building; new commercial permits go through SHAPE PHX.

    IBC 105.1; City of Phoenix
  2. 02

    Low-work exemptions

    Platforms 30 in or lower and racks up to 5 ft 9 in can be exempt, with conditions.

    IBC 105.2 (Phoenix)
  3. 03

    Sealed drawings

    Structural sheets and calculations sealed by an Arizona-registered structural or civil engineer.

    Phoenix submittal checklist
  4. 04

    Fire permit

    Sprinkler and alarm changes need a permit of their own.

    IBC 105.1 (Phoenix)
  5. 05

    One-third of the room

    Combined mezzanine area stays within a third of the room, apart from the listed exceptions.

    IBC 505.2.1
  6. 06

    7 ft clear

    Seven feet of clear height above and below the deck.

    IBC 505.2
  7. 07

    Guards past 30 in

    Open sides more than 30 in above the floor below get guards at least 42 in high.

    IBC 1015.2, 1015.3
  8. 08

    ADOSH at 4 ft

    Fall protection at edges 4 ft or higher, with a 42 in top rail, give or take 3 in.

    29 CFR 1910.28, 1910.29
  9. 09

    Load signs

    Durable signs show the design load on any floor rated over 50 psf, in place before occupancy is approved.

    IBC 106.1, 106.2

02Questions

Mezzanine Permit Questions for Phoenix and Maricopa County

Do I need a Maricopa County permit for a mezzanine?

Only if the building sits in an unincorporated part of Maricopa County. Inside Phoenix the city issues the permit, and the other Valley cities issue their own. For unincorporated areas the county adopted the 2024 I-Codes, effective 20 November 2026, and keeps the 2018 codes through 20 May 2027 for projects already in review.

Source: Maricopa County, 2024 Building Code Implementation

Is a Phoenix mezzanine permit filed in SHAPE PHX?

Yes, for new commercial permits. SHAPE PHX is the City of Phoenix portal for new commercial plan review and inspection permits, in use since April 27, 2026. The city decides how a mezzanine project is classed there; contact Phoenix Planning & Development with questions before filing.

Source: City of Phoenix, SHAPE PHX

Who seals the mezzanine drawings for a Phoenix permit?

A structural or civil engineer registered in Arizona. The Phoenix submittal checklist asks for sealed structural drawings that list the design live loads, the deferred submittals and the special inspections, plus structural calculations sealed by the engineer of record.

Source: City of Phoenix, Commercial Building Permit Submittal Checklist

Does a mezzanine installer in Phoenix need an Arizona contractor license?

Yes, unless the law exempts the job. A.R.S. 32-1151 makes it unlawful to act or bid as a contractor without a license in good standing, and Phoenix asks for the contractor's license number before it issues a commercial permit. We are licensed and insured.

Source: A.R.S. 32-1151; Phoenix submittal checklist

Does a new mezzanine in Phoenix need a separate sprinkler permit?

Yes, when sprinkler or alarm work changes. Phoenix's amended IBC 105.1 calls for separate permits for automatic fire extinguishing systems, fire alarm systems and other equipment the Phoenix Fire Code regulates. For an equipment platform in a building that must be sprinklered, 505.3.2 asks for sprinklers both over and under the platform when the standards cited in Section 903.3 call for them.

Source: IBC 105.1 and 505.3.2, as adopted by Phoenix

Does ADOSH or federal OSHA cover a Phoenix warehouse mezzanine?

ADOSH, for most private and local government workplaces. Arizona runs its own state plan and adopts the federal general industry rules by reference, so the 29 CFR 1910 guardrail, stair and gate rules apply. Federal OSHA keeps federal employers, contractors on some federal establishments and Indian reservations.

Source: OSHA, Arizona State Plan; A.A.C. R20-5-602

03Request for quote

Build Your Quote

Give us the room, the height and the load you have in mind. A Valley installer answers with questions or a written price.

  1. 1You send the floor size, the clear height and the use.
  2. 2We test the plan against IBC 505 and the ADOSH rules.
  3. 3You receive a written quote that lists each step.

Prefer to talk? (928) 232-1752

Free-standing white steel mezzanine with yellow guardrail on four sides and one stair, seen from above

Build Up Inside Your Phoenix Building

  • Rated for what you store.
  • Drawn to the 2024 Phoenix code.
  • Installed around your schedule.
CallRequest a quote