Permit guide · SHAPE PHX

Filing a Mezzanine Permit in Phoenix: SHAPE PHX, Sealed Drawings and Fees, Step by Step

A mezzanine in a Phoenix commercial building needs a commercial building permit, filed online in the City's SHAPE PHX portal. This guide walks the order things happen in, from the first measurements to the load signs, using the City's own checklist and process pages.

Charcoal mezzanine frame part-way up, joists stacked on the floor and two scissor lifts beside it

Does a Mezzanine Need a Commercial Building Permit in Phoenix?

Yes, in almost every case. Section 105.1 of the Phoenix building code says anyone who intends to construct, enlarge or alter a structure must "first make application to the building official and obtain the required permit." The City's commercial permit covers "non-residential construction, including new construction, remodels, additions, tenant improvements, and changes of use." A steel deck inside a warehouse fits that description.

Only narrow exemptions exist, such as platforms of 30 inches or less that sit over no story and serve no accessible route. Our Phoenix permits and code guide covers them, and our quote request form is where to send your floor plan.

Where Do You File a Commercial Permit in Phoenix?

Online, in SHAPE PHX. The City's commercial permit page sends applicants to the SHAPE PHX portal for "NEW Commercial Plan Review and Inspections permits." The SHAPE PHX page dates that change to April 27, 2026. Commercial plan review, permitting and inspections for a new filing all run through the portal.

Which record type a mezzanine goes under is a question to settle with Phoenix Planning & Development before filing. We raise it early on every mezzanine installation in Phoenix we take on, so the package goes in under the right heading.

What Are the Steps From First Visit to Occupancy?

Nine steps, in this order for most projects. The City's process pages and its checklist set the filing steps, and the building code sets the steps on either side of them. How long review takes depends on corrections and resubmittals, so we give the order of events rather than a count of weeks.

  1. Site visit: floor area, clear height, slab, columns and how goods move through the room.
  2. Use and live load chosen from IBC Table 1607.1, such as 125 or 250 psf for storage.
  3. Layout drawn, then sealed by an engineer registered in Arizona, with structural calcs.
  4. Pre-submittal meeting with the City's project team, when it asks for one.
  5. Commercial building permit filed in SHAPE PHX, with plan review fees paid at log-in.
  6. Corrections answered and plans resubmitted until approval; permit fees paid at issuance.
  7. A separate fire permit whenever sprinkler or alarm work changes (IBC 105.1 as amended).
  8. Steel from an approved fabricator, or special inspection in the shop (IBC 1704.2.5).
  9. Installation and inspections, then the posted load signs that the certificate of occupancy waits on.
New charcoal steel beams and deck panels staged inside an open dock door, desert daylight outside
Beams and deck panels staged inside a dock door, ready for the install step.

What Does the Phoenix Submittal Checklist Ask For?

The City's "Commercial Building Permit Submittal Checklist" (TRT/DOC/00029, revised 06/25) sets out the package. For a mezzanine, the structural sheets carry the most weight. The checklist wants structural drawings "Sealed by either a structural or civil engineer registered in the State of Arizona," plus calcs with vertical and lateral analysis sealed by the engineer of record.

  • Project type: new building, new shell, addition, remodel, tenant improvement (T.I.) or miscellaneous work.
  • General notes: design live loads, deferred submittal items, and the special inspection and structural observation requirements.
  • Code data: sprinklers yes or no, fire alarms yes or no, exits required and provided, and the floor the work is on.
  • Remodels and alterations: a structural evaluation or calcs addressing code compliance.
  • Contractor: the license number, which the City needs before it issues the permit on most projects under Arizona law.

The City's process overview adds that licensed professionals prepare the plans for new commercial work. We coordinate the engineer and gather what each line asks for.

When Are Plan Review and Permit Fees Paid in Phoenix?

At two points. Plan review fees come due when the plans are logged in. Permit fees come due when the permit is issued, after review and approval. The checklist ties both to the City's Fee Schedule in Phoenix City Code, Appendix A-2, and the process overview notes that a third review costs extra.

We do not print fee amounts here, because the City sets and updates them. Phoenix Planning & Development can give the current figures for your project.

What Happens Between Submittal and Permit Pickup?

Review, corrections and approval. The City's process overview has the customer contact the project team for a pre-submittal meeting first. After submittal, reviewers check the plans; when corrections are needed, the customer revises and resubmits. Then, "Once approved, staff will create the necessary permits and contact the customer for pick-up."

The City also notes that "a tenant improvement may not have any site issues while a new project or building addition would." Whether your deck is handled as a tenant improvement, an addition or a remodel is settled with the City.

Does Sprinkler or Alarm Work Need Its Own Permit?

Yes. Phoenix's version of Section 105.1 says "Separate permits shall be obtained for automatic fire extinguishing systems, fire alarm systems, and other uses or equipment regulated by the Phoenix Fire Code." So if the deck means moving or adding sprinkler heads or alarm devices, that work is filed on its own.

The building permit and the fire permit move side by side. Our guide to sprinklers under a new mezzanine shows how Valley permit records handle that split.

What Must Happen Before the Deck Goes Into Use?

Inspections, then load signs. Section 106.1 calls for durable signs showing the design live load wherever a commercial or industrial floor is designed above 50 psf. Under Section 106.2, no certificate of occupancy is issued "until the floor load signs, required by Section 106.1, have been installed." Storage rows in Table 1607.1 start at 125 psf, so a storage deck always gets them.

The steel is inspected as well, unless it comes from an approved fabricator. Our guide to special inspections and approved fabricators explains both paths.

Blank aluminium placard on a charcoal mezzanine beam where the load sign goes
A blank placard on the deck fascia marks where the posted live load will read.

Phoenix Permit Questions, Answered

Is a mezzanine permit in Phoenix filed in SHAPE PHX?

Yes, for new commercial plan review. The City's commercial page sends new commercial plan review and inspections permits to the SHAPE PHX portal, effective April 27, 2026. Ask Phoenix Planning & Development which record type fits your project.

Source: City of Phoenix, SHAPE PHX

What do mezzanine permits cost in Phoenix?

The City sets the amounts in its Fee Schedule (Phoenix City Code, Appendix A-2), so we do not print them. Plan review fees are paid at log-in, permit fees at issuance after approval, and a third review costs extra.

Source: City of Phoenix, Commercial Building Permit Submittal Checklist

Does Phoenix need the contractor's license number before issuing a mezzanine permit?

Yes. The City's checklist asks for contractor information, the license number included, before the permit is issued, and notes that Arizona law requires it for most projects.

Source: City of Phoenix, Commercial Building Permit Submittal Checklist

How long does a mezzanine permit take in Phoenix?

It depends on the plans and on how many review rounds they need, so we do not quote a set number of weeks. A complete package, with sealed drawings, calcs and the code data filled in, gives the reviewers everything the checklist asks for from the start.

Source: City of Phoenix, Commercial process overview

Sources, read November 2026: City of Phoenix, Commercial permits · City of Phoenix, SHAPE PHX · City of Phoenix, Commercial process overview · City of Phoenix, Commercial Building Permit Submittal Checklist (Rev. 06/25) · Phoenix Building Code 2024, Chapter 1, via UpCodes · Phoenix Building Code 2024, Table 1607.1, via UpCodes