Special Inspections and Approved Fabricators for Steel Mezzanines in Phoenix
The building code calls for special inspection of fabricated steel while it is being made, unless the shop is approved, and it ties structural steel inspection to the quality assurance rules of AISC 360. Phoenix runs its own approved fabricator program. Here is how the code and the City fit together for a steel mezzanine.

What Is a Special Inspection on a Steel Mezzanine?
It is a check that Chapter 17 of the building code requires for certain structural work, steel included. For structural steel, IBC 1705.2.1 says special inspections and nondestructive testing "shall be in accordance with the quality assurance inspection requirements of AISC 360." The engineer of record lists which inspections apply on the sealed drawings, and plan review checks that list.
For a mezzanine, that means the steel frame: its columns, its beams and the connections between them. See how we plan the frame on our structural steel mezzanines page.

Does Shop Fabrication Need Special Inspection Too?
Yes, unless the fabricator is approved. Section 1704.2.5 says "special inspections of the fabricated items shall be performed during fabrication, except where the fabricator has been approved to perform work without special inspections in accordance with Section 1704.2.5.1." So the shop where the steel is cut, drilled and welded is part of the inspection plan.
Neither 1704.2.5 nor 1705.2.1 appears on Phoenix's list of amended sections, so the 2024 model wording applies to both. Phoenix did amend some other Chapter 17 sections, and plan review applies those as written.
What Is Phoenix's Approved Fabricator Program?
It is the City's route for a steel shop to work without shop special inspections. Phoenix Planning & Development says the program "Ensures the fabricator shop is inspected and accredited by a 3rd party agency." It adds that it "Saves customers time and money by bypassing required special inspections of fabricated products." The City keeps its program resources on its registration and licensing pages.
For a buyer, the practical point is simple. When the steel comes from an approved shop, no special inspector has to visit that shop during fabrication. The other items that move a mezzanine budget, from the load rating to the deck surface, are set out in our mezzanine cost guide.

What Paperwork Closes Out an Approved Fabricator's Work?
A certificate of compliance. Section 1704.2.5.1 says that "At completion of fabrication, the approved fabricator shall submit a certificate of compliance" to the owner or the owner's agent, who passes it to the building official. That certificate joins the rest of the project record.
If the steel comes from a shop outside the program, special inspection happens during fabrication under 1704.2.5 instead. Either way, we gather the steel paperwork so it can go to the building official with the other closeout documents.
Where Do Inspections Show Up on the Drawings?
In the general notes of the sealed structural set. Phoenix's commercial checklist wants structural drawings sealed by a structural or civil engineer registered in Arizona. Their general notes list the "Design Live Loads," every deferred submittal item, and "all Special Inspection and Structural Observation requirements." The calcs, sealed by the engineer of record, cover vertical and lateral analysis.
- Shop: an approved fabricator, or special inspection during fabrication.
- Steel work: inspection and testing to the AISC 360 quality assurance rules (1705.2.1).
- Deferred items: parts such as steel joists that the engineer submits later, named up front.
- Closeout: the certificate of compliance or the inspection reports, then the posted load signs.
What Does the Engineer Need From You Before the Steel Is Sized?
The use of the deck and what it will carry. The engineer of record picks the live load from IBC Table 1607.1, where light storage starts at 125 psf, offices at 50 psf and service catwalks at 40 psf. Section 1607.3 says design loads "shall be the maximum loads expected by the intended use or occupancy," so heavier goods push the steel up. The inspections are then written against that design.
- What goes on the deck, and how much a full pallet, bin or rack weighs.
- Carts, pallet jacks, conveyors or machines that stand on the deck.
- Whether the work is a remodel: Phoenix's checklist asks for a structural evaluation or calcs for remodels and alterations.
- Any part you expect to add later, so it can be listed as a deferred submittal.
A floor designed above 50 psf also needs posted load signs before the certificate of occupancy, so the load you choose carries through to closeout.
What Do Valley Permit Records Show?
That special inspection shows up as a named line on mezzanine permits. City permit records in Mesa, a public dataset, list it on recent jobs. These are other owners' projects, quoted only to show how permits word it, with every name left out. Mesa runs its own permit office, so the lines show practice there, not Phoenix rules.
- 2025: an office mezzanine added inside a large warehouse lists "Special inspection req. - steel, concrete, Deep foundations" and a deferred submittal for steel joists.
- 2025: an expanded storage mezzanine lists "Special inspections for steel construction, concrete construction, and epoxy."
How Do We Plan the Steel Side of the Job?
We settle the inspection path before steel is ordered. Either the steel comes from an approved fabricator, with its certificate of compliance at the end, or the shop inspections are booked as part of the plan. The engineer's notes, the deferred items and the site inspections then line up with the install schedule.
You place one order with us for the mezzanine, and our own crew erects it once the steel and its paperwork are ready. The full scope is on our Phoenix mezzanine installers page.
Steel Inspection Questions, Answered
Does a steel mezzanine in Phoenix need special inspections?
Plan on it. IBC 1705.2.1 ties structural steel inspection to AISC 360, and 1704.2.5 calls for inspection during fabrication unless the fabricator is approved. The engineer lists the requirements on the sealed drawings, and plan review checks them.
Source: IBC 1704.2.5 and 1705.2.1
What does an approved fabricator save on a mezzanine job in Phoenix?
The shop inspections. Phoenix says its program saves customers time and money by bypassing required special inspections of fabricated products, and the fabricator submits a certificate of compliance when fabrication is done.
Source: City of Phoenix, Approved fabricator resources; IBC 1704.2.5.1
Did Phoenix amend the steel inspection sections of the IBC?
Not 1704.2.5, 1704.2.5.1 or 1705.2.1; none of them appears on the City's 2024 amendment list, so the model wording applies. Phoenix did amend some other Chapter 17 sections, which plan review applies as written.
Source: City of Phoenix, 2024 IBC amendment sheets
Who seals the steel drawings for a mezzanine in Phoenix?
A structural or civil engineer registered in the State of Arizona, per the City's commercial submittal checklist. The sealed set lists the design live loads, the deferred submittals and the special inspections.
Source: City of Phoenix, Commercial Building Permit Submittal Checklist
Sources, read November 2026: Phoenix Building Code 2024, Chapter 17 special inspections, via UpCodes · Phoenix Building Code 2024, Table 1607.1, via UpCodes · Phoenix Building Code 2024, Chapter 1, via UpCodes · City of Phoenix, Approved fabricator resources · City of Phoenix, Commercial Building Permit Submittal Checklist (Rev. 06/25) · City of Phoenix, 2024 IBC amendment sheets · City of Mesa open data, Building Permits (retired set)