Structure guide · Slabs and footings
Can a Phoenix Warehouse Slab Carry a Mezzanine? Footings, Base Plates and Anchors
Every mezzanine column ends in a steel base plate anchored to concrete, and that concrete, with the soil under it, has to carry the load. Whether your existing slab can, or the job needs new footings, is answered by the engineer for your building. This guide shows what that check covers under the 2024 code Phoenix enforces, including two rules the City added for post-tensioned slabs.

How Does a Mezzanine's Weight Reach the Ground?
Through its columns. The deck hands its load to the joists, the joists to the beams and the beams to the columns, and each column sets it down on a steel base plate fastened to the concrete. A load spread across the whole deck therefore arrives at the slab as a handful of heavy points. Take a column holding up a 20 by 20 foot share of a light-storage deck: at the 125 psf minimum in IBC Table 1607.1, the live load on that share alone is 50,000 lb, before the steel and decking add their own weight.
That is an illustration only; the engineer works out the real figures for your layout. Column grids and framing are on our structural steel mezzanines page.

How Thick Must a Slab Be Under a Mezzanine?
No code table answers that for a mezzanine; the engineer works it out from the column loads, the base plates, the concrete and the soil beneath. The one fixed figure is the minimum for every floor slab on the ground: "The thickness of concrete floor slabs supported directly on the ground shall be not less than 3 1/2 inches (89 mm)." It applies to every slab, loaded or not. Section 1907.1 adds that a slab-on-ground is structural concrete where it is designed to transmit "Vertical loads or lateral forces from other parts of the structure to the soil." Structural concrete is then designed to Chapter 19 and ACI 318.
So the engineer needs to know what your slab really is, and the building's original drawings are the first place to look.
What Does the Phoenix Code Say About the Soil Under a Slab?
It gives starting bearing values for each class of soil, then leaves the rest to the engineer and the building official. Table 1806.2 lists presumptive vertical foundation pressures, from 1,500 psf for clays and silts up to 12,000 psf for crystalline bedrock, and higher values need supporting data that the City approves. Phoenix's version of Section 1806.2 says undocumented fill "shall not be assumed to have a presumptive load-bearing capacity" unless data backs a value. In areas likely to have expansive soil, the building official requires soil tests (1803.5.3).
| Class of material | Vertical foundation pressure |
|---|---|
| Crystalline bedrock | 12,000 psf |
| Sedimentary and foliated rock | 4,000 psf |
| Sandy gravel and gravel (GW, GP) | 3,000 psf |
| Sand, silty sand, clayey sand, silty gravel and clayey gravel (SW, SP, SM, SC, GM, GC) | 2,000 psf |
| Clay, sandy clay, silty clay, clayey silt, silt and sandy silt (CL, ML, MH, CH) | 1,500 psf |
Phoenix also lets the building official waive a geotechnical investigation for "lightweight or temporary structures where reasonable presumptive load bearing values are used." Whether a given mezzanine qualifies is the City's call.
When Does a Mezzanine Need New Footings?
When the engineer's calculations show the slab or the soil beneath it cannot take a column's load as it stands. Every foundation must meet one test: it "shall be so designed that the allowable bearing capacity of the soil is not exceeded, and that differential settlement is minimized" (IBC 1808.2). A new footing must bear on undisturbed soil, compacted fill or controlled low-strength material (1809.2). Section 1809.4 sets 12 inches as the least depth below undisturbed ground and the least width for any footing; a footing under a loaded column is sized from that column's load, not from those minimums.
Foundation work does turn up on Valley mezzanine permits. A 2025 City of Mesa permit for a 4,000 sq ft office mezzanine inside a warehouse lists special inspection of "steel, concrete, Deep foundations."
What If the Slab Is Post-Tensioned?
Then the tendons are located before anyone drills or cuts, and Phoenix's code makes such a slab easier to recognize. The City amended Section 1907.5 so that "All post-tensioned slabs on ground shall be permanently stamped, marked, or otherwise identified in a conspicuous location". Its stated reason: a cut tendon "can cause serious injury to people in the area," and the mark tells the contractor "to identify tendon locations prior to cutting or drilling into the slab." The marking rule reaches nonstructural slabs too (1907.2).
For a mezzanine, the anchor holes and any footing cut-outs are laid out around the tendons. We look for the mark at the site visit and ask for the slab drawings.
Which Anchors Hold a Mezzanine Column to the Concrete?
The anchors the engineer specifies, designed to ACI 318 as the code requires. IBC 1901.3 says anchoring to concrete follows ACI 318 and lists the types it covers: cast-in headed bolts, headed studs and hooked J- or L-bolts, and post-installed expansion, undercut, screw and adhesive anchors. In an existing slab the anchors are post-installed in drilled holes, while a new footing can take bolts cast into the pour. The plate and the anchor type, size, depth and spacing come from the sealed design.
Columns in forklift aisles also get a steel guard at the base, bolted down around the plate.

Who Inspects the Anchors and the Concrete Work?
A special inspector, wherever Table 1705.3 calls for one. The table sets periodic inspection for anchors cast in concrete and for most post-installed anchors, and continuous inspection for adhesive anchors set horizontally or angled upward to resist sustained tension. Where the anchor's research report gives no specific inspection requirements, the registered design professional specifies them, and the building official approves them before work starts.
- Anchors cast in concrete: periodic (Table 1705.3, row 3).
- Adhesive anchors installed horizontally or angled upward under sustained tension: continuous (row 4a).
- Mechanical anchors and other adhesive anchors: periodic (row 4b).
A 2025 Mesa permit to expand a warehouse mezzanine calls for special inspections "for steel construction, concrete construction, and epoxy." Our special inspections guide covers the steel side.
What Does the Engineer Need to Size the Footings and Anchors?
The deck's use, the column layout and whatever you know about the slab and the soil. Phoenix's commercial checklist wants structural drawings sealed by a structural or civil engineer registered in Arizona, calculations covering vertical and lateral analysis, and, for remodels and alterations, a "structural evaluation/calculations addressing code compliance." The engineer of record sizes the footings, base plates and anchors for each building from that evaluation. Where the code requires a soil investigation, its report goes in with the permit application and gives the bearing capacity and any measures for expansive soil (1803.6).
- The building's original drawings, or any soil report from its construction.
- Any post-tensioning stamp or mark on the slab.
- Trenches, pits, joints or patched areas where columns might land.
- What the deck will carry, and where pallets, carts or machines will sit.
Send those with your quote request, and we line up the engineer before steel is ordered. Start from our Phoenix mezzanine installers page.
Slab and Footing Questions from Phoenix Buildings
Will my existing Phoenix warehouse slab hold a mezzanine?
Often, but only the engineer's check of your building can say so. Each column loads a small area of concrete, so the engineer weighs the slab's real thickness, the soil and the column loads, then calls for footings wherever the slab falls short.
Source: IBC 1808.2, 1907.1
Does a mezzanine in Phoenix need a soil report?
Not always. The code calls for geotechnical investigations under Section 1803, and Phoenix lets the building official waive one for lightweight or temporary structures that use presumptive values. In areas likely to have expansive soil, soil tests are required, and the building official can ask for an investigation wherever the soil's class or strength is in doubt.
Source: IBC 1803.2 as amended by Phoenix, 1803.5.2, 1803.5.3
Can anchors be drilled into a post-tensioned slab in Phoenix?
Only once the tendons have been located. Phoenix requires post-tensioned slabs to be permanently marked so contractors find the tendons before cutting or drilling, and the engineer places the anchors and any footing cut-outs clear of them.
Source: IBC 1907.5 as amended by Phoenix
Who designs mezzanine footings in Phoenix?
The engineer of record for the mezzanine. Phoenix wants the structural drawings sealed by a structural or civil engineer registered in Arizona, with calculations, and the general notes list every special inspection, the concrete and anchor work included.
Source: City of Phoenix, Commercial Building Permit Submittal Checklist
Sources, read November 2026: Phoenix Building Code 2024, Chapter 18 soils and foundations, via UpCodes · Phoenix Building Code 2024, Chapter 19 concrete, via UpCodes · Phoenix Building Code 2024, Chapter 17 special inspections, via UpCodes · Phoenix Building Code 2024, Table 1607.1, via UpCodes · City of Phoenix, 2024 IBC amendment sheets · City of Phoenix, Commercial Building Permit Submittal Checklist (Rev. 06/25) · City of Mesa open data, Building Permits (retired set)