Planning guide · Project timeline
From Site Visit to Final Inspection: How Long a Phoenix Mezzanine Takes
Nobody can honestly give a finish date for a mezzanine before its drawings exist. What can be known is the order of the stages, which of them overlap, and the review limits the City of Phoenix publishes for itself. This guide sets out all three, so you can plan the months around your own deck.

What Decides How Long a Phoenix Mezzanine Takes?
Three things: how complete the drawings are when they reach the City, how many review rounds they need, and how soon the steel can be made and delivered. The first two belong to the permit, and Phoenix prints its own limits for them. The third belongs to the order, so we date it in your quote once the design is fixed. The install comes last. By the time the crew arrives, the layout, the slab check and the permit are already settled.
The filing steps themselves are in our guide to filing a mezzanine permit in SHAPE PHX. This guide is about time.
What Are the Stages of a Phoenix Mezzanine Project?
Seven, and two of them run side by side. Planning and sealed drawings come first. City plan review follows, with the fire permit moving on its own track when sprinklers or alarms change. Steel is made once the plans are approved, then delivered and installed, and the job closes with inspections and posted load signs. The table shows what each stage holds and what sets its pace.
| Stage | What happens | What sets its pace |
|---|---|---|
| Site visit and layout | Room size, clear height, slab, the deck's use and its live load | How quickly the use and the heaviest load are agreed |
| Sealed drawings | Structural drawings and calculations sealed by an Arizona-registered engineer | Deck size, loads and any slab or footing question |
| City plan review | Administrative check, then substantive review, filed in SHAPE PHX | The City's published time frames and the number of review rounds |
| Fire permit | Sprinkler or alarm changes, filed on their own | A separate review time frame, running beside the building review |
| Steel | Fabrication by an approved fabricator, or with special inspection in the shop | The order and the fabrication schedule |
| Install | Columns, beams, deck, stairs, rails and gates | Deck area, access to the room and your operation around the crew |
| Close-out | Inspections, load signs, and a certificate of occupancy where one is required | Inspection dates and the signs going up |
How Long Does Phoenix Plan Review Take?
The City's published limit is 10 calendar days for the administrative check of a commercial plan, then 50, 70 or 90 days of substantive review, depending on the project's size and value. Planning & Development sets those figures in its time frame policy under A.R.S. 9-835. The substantive window covers the first full review and one more review after corrections. By mutual agreement, the City and the applicant may stretch the substantive and overall time frames by up to 50 percent. These are the City's limits, not a forecast for your deck.
| Review class | Square feet | Valuation | Administrative | Substantive |
|---|---|---|---|---|
| Major | Over 50,000 | Over $5,000,000 | 10 days | 90 days |
| Medium | 5,000 to 50,000 | $350,000 to $5,000,000 | 10 days | 70 days |
| Minor | Under 5,000 | Under $350,000 | 10 days | 50 days |
| All revisions | Any | Any | 10 days | 50 days |
The area and valuation on your application decide the row.
Does the Fire Permit Add Time to a Phoenix Mezzanine?
It runs next to the building review, so it adds the least time when it starts on day one. Phoenix's amended IBC 105.1 calls for separate permits for automatic fire extinguishing systems and fire alarm systems. The City's time frame policy gives fire prevention plan review its own limits: 10 days administrative and 60 days substantive for a new submittal or a modification. Valley records show the split. A 2025 City of Mesa permit for an office mezzanine in a warehouse lists "Deferred fire sprinklers and fire alarms," so those plans followed the main set.
How the sprinkler work is permitted is in our guide to sprinklers under a new mezzanine.
What Are Deferred Submittals, and Do They Slow the Job?
They are pieces of the design sent in after the main plans, and they let the main review start sooner. Phoenix's Section 107.3.4.1 needs the building official's approval to defer anything, and the engineer lists the deferred items on the drawings. The City's checklist asks the general notes to "Identify all Deferred Submittal Items." Valley records show joists and sprinklers deferred this way: a 2025 Mesa permit reads "Deferred submittal - steel joist." One rule keeps the order honest: deferred items "shall not be installed until the deferred submittal documents have been approved by the building official."
How Long Does a Phoenix Plan Review Stay Open?
Twelve months from filing, unless it is pursued in good faith or a permit is issued. The City's expiration policy says an application otherwise "shall be deemed to have been abandoned 12 months after the date of filing," and it allows extensions of up to 180 days each, asked for in writing with justifiable cause and a fee. Corrections are not accepted on an expired review without an extension. Once issued, a Phoenix building permit expires 24 months after issuance unless the City extends it in writing (IBC 105.5 as amended).
How Long Do the Steel and the Installation Take?
That depends on the design, so your quote gives the dates for your deck rather than a general guide. Fabrication starts from approved drawings. When the steel comes from a City-approved fabricator, the shop special inspections are skipped; otherwise a special inspector checks the fabricated items during fabrication (IBC 1704.2.5). Installation follows the deck area, the stairs and gates, how the steel reaches the room, and whether your operation keeps running around the crew. We set the install sequence around your shifts at the site visit.

What Has to Happen Before the Deck Goes Into Use?
Final inspections, then posted load signs, then a certificate of occupancy wherever the City requires one. Phoenix's certificate of occupancy page lists new commercial structures, a tenant improvement of a newly occupied space, and a tenant improvement or remodel that changes the occupancy type, plus "Other projects as determined." Under IBC 106.2, a certificate is not issued "until the floor load signs, required by Section 106.1, have been installed," and any commercial or industrial floor rated above 50 psf needs them. The City also takes temporary certificate of occupancy applications on active permits.

What Keeps a Phoenix Mezzanine on Schedule?
A complete first submittal, because review rounds take the most time and the City charges extra for a third review. Most of what makes a submittal complete is known before the engineer starts, from the deck's use to the building's own records. These five items do the most to keep the job moving.
- Agree on the deck's use and its heaviest load before drawings begin.
- Find the building's original drawings and any slab or soil report.
- Say early whether sprinklers or alarms will change, so the fire permit starts with the building permit.
- Ask Phoenix Planning & Development which record type fits the project before filing.
- Answer correction notices quickly, inside the 12-month window.
Budget figures for the deck itself are in our mezzanine cost guide, and the full scope of our work is on the Phoenix mezzanine installation page.
Phoenix Mezzanine Timing Questions, Answered
How long does it take to get a mezzanine permit in Phoenix?
The City's published limits for commercial plan review are 10 calendar days for the administrative check and 50, 70 or 90 days of substantive review, set by the project's size and value. The substantive window covers one full review and one more after corrections. They are limits, not a forecast.
Source: City of Phoenix, License Time Frames A.R.S. 9-835 Policy
Can mezzanine work start in Phoenix before the permit is issued?
No. IBC 105.1 has the owner apply for and obtain the permit before the structure is built. Fabrication is released once the drawings are approved.
Source: IBC 105.1
Does a new mezzanine in Phoenix need a certificate of occupancy?
Sometimes. The City lists new commercial structures, tenant improvements of a newly occupied space, and tenant improvements or remodels that change the occupancy type, plus other projects it decides. Where a certificate is issued, it waits for the load signs on any floor rated above 50 psf.
Source: City of Phoenix, Certificate of Occupancy; IBC 106.2
What happens if a Phoenix plan review sits idle?
The City treats the application as abandoned 12 months after filing unless it is pursued in good faith or a permit is issued. Extensions of up to 180 days each can be asked for in writing, with justifiable cause and a fee.
Source: City of Phoenix, Plan Review Expiration Policy
Sources, read November 2026: City of Phoenix, License Time Frames A.R.S. 9-835 Policy (New 09/25) · City of Phoenix, Plan Review Expiration Policy · City of Phoenix, Certificate of Occupancy · City of Phoenix, Commercial/Multi-family Permit/Plan Review Application · City of Phoenix, Commercial Building Permit Submittal Checklist (Rev. 06/25) · City of Phoenix, Commercial process overview · City of Phoenix, Approved fabricator resources · Phoenix Building Code 2024, Chapter 1, via UpCodes · Phoenix Building Code 2024, Chapter 17 special inspections, via UpCodes · City of Mesa open data, Building Permits (retired set)