Load rows · 2024 IBC in Phoenix

Catwalk, Walkway or Storage Deck? Picking the Right Row in IBC Table 1607.1

A raised level in a Phoenix plant or warehouse is rated for what people do on it, not for what it is called. This guide walks through the Table 1607.1 rows that fit catwalks, walkways, platforms and storage decks, using the 2024 edition the city enforces.

Galvanised bar-grating deck with sunlight casting a grid of shadows on the floor below

Why Does the Work on a Deck Decide Its Live Load?

Because Table 1607.1 is organized by occupancy and use, and the word mezzanine is not one of its rows. A raised level borrows the row that matches its daily work. Section 1607.3 says design loads "shall be the maximum loads expected by the intended use or occupancy but shall not be less than the minimum uniformly distributed live loads given in Table 1607.1." So the table sets a floor, and your real use can push the number higher.

Phoenix enforces the 2024 Phoenix Building Construction Code, which adopts the 2024 IBC and took effect on August 1, 2025. For the walkway side of this question, see warehouse catwalk systems in Phoenix. For the storage side, see warehouse storage platforms.

How Much Must a Service Catwalk Carry in Phoenix?

A catwalk used only for maintenance and service access is designed for 40 psf or more, and a single 300 lb concentrated load is checked as well. That is row 6 of the 2024 table. It fits a narrow route to air handlers, lights, valves or conveyor drives, where a technician walks with a tool bag and little else.

The row has a narrow scope. Once people stage parts, carry cartons or stand at a station on the walkway, it no longer describes a service route, and a heavier row takes over. A walkway that exists only to reach an equipment platform can also be part of that platform: the code defines an equipment platform as including "the associated elevated walkways, stairways, alternating tread devices and ladders necessary to access the platform."

Grating catwalk with yellow guardrail along a high wall, giving access to overhead air units
A grating service walkway along a high wall, reaching overhead air units.

When Does a Walkway Move Up to the 60 psf Row?

When it is a working walkway or elevated platform rather than a service catwalk. Row 37 of Table 1607.1 lists "Walkways and elevated platforms (other than exitways)" at 60 psf. That covers a crossover people use through the shift, a staging platform beside a line, or a walk deck that pickers cross many times a day.

Note the words "other than exitways." A route that forms part of the exit path falls outside row 37. The stairs and exits row sets 100 psf with a 300 lb concentrated load for buildings other than one- and two-family homes. Plan review confirms which row each route takes, so mark exit routes on the layout early.

What Rating Does a Storage Deck or Elevated Storage Platform Take?

Row 34 of the 2024 table sets 125 psf as the light storage minimum and 250 psf as the heavy one. The row carries its own warning: storage warehouses "shall be designed for heavier loads if required for anticipated storage." So dense, heavy stock can call for more than 250 psf.

The table names the two tiers but leaves the sorting to your engineer, who works from what you store and how it moves. Two nearby rows also matter for raised floors. Wholesale stores take 125 psf on all floors, with a 1,000 lb concentrated load. Manufacturing floors take 125 psf light or 250 psf heavy, with 2,000 lb or 3,000 lb concentrated loads.

Dark resin-board panels on a mezzanine deck with a pallet jack and a pallet of cartons
A pallet jack and a pallet of cartons on a resin-board storage deck.

Which Table 1607.1 Rows Fit Raised Floors in a Plant or Warehouse?

Nine rows cover most raised levels found in plants and warehouses. The values below are minimum uniform live loads from the 2024 numbering of Table 1607.1, which is the table Phoenix plan reviewers read. Where a row also lists a concentrated load, it appears in the right-hand column. Your engineer still checks wheel loads, conveyor legs and rack posts against the design, since a uniform value spreads weight evenly and real equipment does not.

Table 1607.1 Rows for Raised Floors in Valley Buildings2024 IBC Table 1607.1, Phoenix edition via UpCodes. Row numbers follow the 2024 table.
Use on the raised levelRowMinimum uniform loadConcentrated load
Catwalk for maintenance and service access640 psf300 lb
Walkway or elevated platform, not an exitway3760 psfUniform value only
Offices2350 psf2,000 lb
Office corridors above the first floor2380 psf2,000 lb
Stairs and exits, other than homes32100 psf300 lb
Gymnasium26100 psfUniform value only
Manufacturing, light or heavy21125 or 250 psf2,000 or 3,000 lb
Storage warehouse, light or heavy34125 or 250 psfUniform value only
Wholesale store, all floors35125 psf1,000 lb

What If One Deck Serves Two Uses?

Then each zone is rated for its own use, or the whole deck is rated for the heavier one. A deck with a parts aisle and a small office can carry 125 psf in the aisle and 50 psf under the office. Splitting the rating can save steel, but it locks the layout. A single, higher rating costs more up front and leaves you free to move things later.

Think about the next tenant, too. The design load is the "maximum loads expected by the intended use," so a deck rated for offices is not a storage deck. In commercial and industrial buildings, Section 106.1 requires durable posted signs for any floor or portion designed above 50 psf. Every storage row sits above that line, and a 40 psf service catwalk sits below it.

Did Phoenix Change Any Commercial Loads in Table 1607.1?

No. The City's 2024 IBC amendment sheets touch Table 1607.1 in one place: the residential row for one- and two-family dwellings. No commercial or industrial row is changed, and Section 505 on mezzanines is not amended either. So the values in this guide are the 2024 IBC values exactly as printed.

The final number belongs on the structural drawings. Phoenix's commercial submittal checklist asks for "Design Live Loads" in the general notes of drawings sealed by an Arizona-registered structural or civil engineer. We gather your use, weights and traffic, the engineer sets the rating, and our crew installs the steel to match. Start with our mezzanine installation in Phoenix page if you are still sizing the project.

Table 1607.1 in Phoenix: Common Questions

What is the live load for a catwalk in Phoenix?

A catwalk used for maintenance and service access is designed for 40 psf or more, and for a 300 lb concentrated load. That is row 6 of 2024 IBC Table 1607.1, which Phoenix has enforced since August 1, 2025. A catwalk used for picking or staging takes a heavier row.

Source: 2024 IBC Table 1607.1, row 6

Does a Phoenix storage mezzanine have to be rated at 125 psf?

That is the minimum for light storage. Heavy storage starts at 250 psf, and the table says storage floors must be designed heavier when the expected goods require it. Your engineer picks the tier from what you will store.

Source: 2024 IBC Table 1607.1, row 34

What load do walkways and crossovers in Phoenix plants carry?

Walkways and elevated platforms other than exitways start at 60 psf under row 37. A route that serves as an exit falls under the stairs and exits row instead, at 100 psf with a 300 lb concentrated load.

Source: 2024 IBC Table 1607.1, rows 32 and 37

Who picks the Table 1607.1 row for a Phoenix project?

The engineer of record does, and Phoenix plan review checks it. The city's submittal checklist asks for the design live loads in the general notes of structural drawings sealed by an Arizona-registered structural or civil engineer.

Source: City of Phoenix Commercial Building Permit Submittal Checklist

Sources, read November 2026: Phoenix Building Code 2024, Table 1607.1, via UpCodes · Phoenix Building Code 2024, Chapter 2 definitions, via UpCodes · Phoenix Building Code 2024, Chapter 1, via UpCodes · City of Phoenix, 2024 IBC amendment sheets · City of Phoenix, 2024 PBCC implementation notice · City of Phoenix, Commercial Building Permit Submittal Checklist (Rev. 06/25)

Rate Your Deck for the Work It Will Carry

Tell us who walks on the deck, what sits on it and what rolls across it. We take that to the engineer for the rating, then supply the steel and install it with our own crew.

CallRequest a quote